When contracting maintenance or subcontracting any part of its continuing-airworthiness management, the CAMO must ensure that the activities conform to the applicable requirements and that associated aviation safety hazards are considered within its management system.
Subcontracting continuing-airworthiness management tasks
When the CAMO subcontracts continuing-airworthiness management tasks, the subcontracted organisation works under the CAMO's approval, and the CAMO must ensure that the authority can access the subcontracted organisation to determine continued compliance. Under CAMO.A.125(d)(3), limited continuing-airworthiness tasks may be arranged with a subcontracted organisation working under the CAMO's management system, within the scope stated on the certificate and in the CAME.
Subcontracting these limited tasks does not transfer the CAMO's responsibility for conformity, and it does not permit subcontracting the airworthiness review itself: M.A.901(g) and ML.A.901(g) prohibit that.
Control procedures, competence and access
The CAME must contain procedures controlling contracted and subcontracted activities under CAMO.A.205 and CAMO.A.315(c). The management system's compliance-monitoring function and the necessary corrective-action feedback cover the applicable requirements. The CAMO must establish and control the competency of relevant personnel in accordance with a procedure and to a standard agreed by the authority, including an appropriate understanding of safety management and human factors.
Under CAMO.A.140, relevant facilities, aircraft, documents, records, data, procedures and other material relevant to the certified activity, whether contracted or subcontracted or not, must be accessible at any time to persons authorised by the competent authority or by the oversight authorities specified in CAMO.B.300(d) or (e).
Contracted maintenance
Maintenance contracting is distinct from subcontracting management tasks, but it is still covered by CAMO.A.205(a). Where the CAMO is not appropriately approved for maintenance, it must, in consultation with the operator, manage the written maintenance contracts required by M.A.201(e)(3), (f)(3), (g)(3) and (h)(3) or ML.A.201, so that maintenance is ultimately performed by an appropriately approved organisation and the specified M.A.301 or ML.A.301 functions are clear.
Notwithstanding CAMO.A.315(c), individual work orders addressed to the maintenance organisation may serve as the contract for unscheduled line maintenance or for component maintenance, including engine and propeller maintenance, as applicable. The historical reference to Subpart F approvals that still appears in CAMO.A.315 does not revive those approvals: Article 4(2) made them cease to be valid on 24 March 2022. Use the applicable current maintenance-approval route.
Human factors and contract records
Human factors and human-performance limitations must be taken into account in continuing-airworthiness management, including all contracted and subcontracted activities. Contracts for both contracting and subcontracting must be retained for at least five years under CAMO.A.220(b)(2).
Application dates
The CAMO.A.205 requirements have applied since 24 March 2020 (Commission Implementing Regulation (EU) 2019/1383, as corrected). The contract-function wording in CAMO.A.315(c)(2) was amended separately (Commission Implementing Regulation (EU) 2020/270, applicable from 24 March 2020), and the business-grouping arrangements in CAMO.A.125 and CAMO.A.200 were amended by Commission Implementing Regulation (EU) 2022/410, applicable from 31 March 2022. No later application date applies to the unchanged CAMO.A.205 duties.