CAMO.A.115 — Application for an organisation certificate

On this page
Regulation section

Applications for a certificate or its amendment use the competent authority’s form and manner. Initial applicants must provide their own pre-audit results and compliance documentation, including the procedure for managing and notifying changes not requiring prior approval.

Applying for a Part-CAMO certificate

Before a Part-CAMO approval can be granted, the applicant must submit a completed application to the competent authority in the form and manner that authority prescribes.

CAMO.A.115(b) requires initial applicants to provide pre-audit results and documentation demonstrating compliance, including the procedure for changes not requiring prior approval. Separately, CAMO.A.300 requires the organisation to provide its CAME and applicable referenced manuals and procedures, and CAMO.B.310 requires formal approval of the CAME during initial certification. The precise arrangement for submitting the application pack at the same time is authority-specific and is not expressly listed in CAMO.A.115(b).

This exposition (the CAME) is the cornerstone of the approval process because it demonstrates how the organisation intends to comply with every requirement of Part-CAMO.

The CAMO.A.300 duty is to provide the CAME and applicable associated manuals and procedures to the competent authority, not merely to have an internal document. Its initial issue must be approved. Personnel qualification and availability, facilities and the full applicable compliance duties are not waived by the CAMO.A.115 application requirements.

Initial applicants provide the pre-audit results and compliance documentation required by CAMO.A.115(b). Under CAMO.A.300, the CAME provided to the authority includes the scope of work, the specified personnel, a description of manpower resources and the system for planning staff availability, and a general description and location of the facilities; the actual personnel and facility requirements remain those of CAMO.A.305 and CAMO.A.215. Follow the competent authority’s form and manner rather than treating this page as an exhaustive checklist for the application pack.

Scope of work and terms of approval

The organisation’s scope of work is specified in the CAME under CAMO.A.125(c) and CAMO.A.300(a)(3); the privileges, the scope of the activities that the organisation is approved to conduct and any limitations as applicable are specified in the terms of approval attached to the certificate under CAMO.B.310(g). The competent authority establishes the form and manner of the application under CAMO.A.115(a).

How the competent authority verifies compliance

The competent authority verifies compliance under CAMO.B.310 using the organisation’s application and compliance documentation; its oversight system includes assessments, audits and inspections under CAMO.B.300.

The competent authority will conduct an initial assessment before granting the approval.

Text of CAMO.A.115 and CAMO.B.310

CAMO.A.115 Application for an organisation certificate (a) The application for a certificate or an amendment to an existing certificate in accordance with this Annex shall be made in a form and manner established by the competent authority, taking into account the applicable requirements of Annex I (Part-M), Annex Vb (Part-ML) and this Annex. (b) Applicants for an initial certificate pursuant to this Annex shall provide the competent authority with: (1) the results of a pre-audit performed by the organisation against the applicable requirements provided for in Annex I (Part-M), Annex Vb (Part-ML) and this Annex; (2) documentation demonstrating how they will comply with the requirements established in this Regulation. Such documentation shall include, as provided for in point CAMO.A.130, a procedure describing how changes not requiring prior approval will be managed and notified to the competent authority.

CAMO.B.310 Initial certification procedure (a) Upon receiving an application for the initial issue of a certificate for an organisation, the competent authority shall verify the organisation's compliance with the applicable requirements. (b) A meeting with the accountable manager of the organisation shall be convened at least once during the investigation for initial certification to ensure that he/she fully understands the significance of the certification process and the reason for signing the statement of the organisation to comply with the procedures specified in the CAME. (c) The competent authority shall record all findings, closure actions (actions required to close a finding) and recommendations. (d) The competent authority shall confirm in writing all the findings raised during the verification to the organisation. For initial certification, all findings must be corrected to the satisfaction of the competent authority before the certificate can be issued. (e) When satisfied that the organisation complies with the applicable requirements, the competent authority shall: (1) issue the certificate as established in Appendix I ‘EASA Form 14’ to this Annex; (2) formally approve the CAME. (f) The certificate reference number shall be included on the EASA Form 14 certificate in a manner specified by the Agency. (g) The certificate shall be issued for an unlimited duration. The privileges, scope of the activities that the organisation is approved to conduct, including any limitations as applicable, shall be specified in the terms of approval attached to the certificate. (h) To enable the organisation to implement changes without prior competent authority approval in accordance with point (c) of point CAMO.A.130, the competent authority shall approve the relevant CAME procedure defining the scope of such changes and describing how such changes will be managed and notified.

When these rules apply

CAMO.A.115 and CAMO.B.310 have applied since 24 March 2020. The current CAME content requirements have separately dated parts; the evaluation-programme amendments of 7 August 2026 do not change the date of the CAMO.A.115 pre-audit duty.

Part CAMO Training

Building a compliant CAMO operation?

Sofema's Part CAMO course covers SMS obligations, airworthiness review processes, and the management system requirements for continuing airworthiness organisations.

View Part CAMO course

Sources

Next step Sofema Aviation Academy

Courses for CAMO.A.115

EASA Part CAMO Safety (SMS) & Human Factors (HF) Training (Initial) with VO

3 days · Voice Over

Why: covers the approval, findings and continued-validity requirements for Part-CAMO.

View course

More on this subject

Related training, not a regulatory requirement. Check course scope and prerequisites before enrolling.

A different role or training goal? Course Finder

Educational reference, not legal advice. Verify against the current Official Journal text linked under Sources. How this hub is made.