145.A.85 requires prior formal approval by the competent authority for the changes it specifies and for every other Part-145 change requiring prior approval. All changes not requiring prior approval must be managed and notified under the procedure approved by the competent authority.
What 145.A.85 requires
Classify changes using the prior-approval categories in 145.A.85 and the approved procedure for changes not requiring prior approval, not a free-standing "significant change" threshold. Where prior approval is required, formal approval must be received before the change is implemented; for changes not requiring prior approval, timing is set by the approved procedure.
The purpose is to ensure the competent authority can assess whether the changed organisation still meets the approval requirements.
Changes requiring prior approval
145.A.85(a) lists five classes of change: changes to the certificate, including the terms of approval; changes of the persons referred to in 145.A.30(a), (b), (c) and (ca); changes to the reporting lines between the personnel nominated under 145.A.30(b), (c) and (ca) and the accountable manager; the procedure for changes not requiring prior approval; and additional locations of the organisation, except those subject to 145.A.75(c). For other examples, apply the facts of the actual certificate, MOE and procedures rather than assuming a statutory "quality manager" title or a single notification category.
Under 145.A.85(a)(1) to (3), prior approval covers changes to the certificate, including the terms of approval; changes of the persons referred to in 145.A.30(a), (b), (c) and (ca); and changes to the reporting lines between the personnel nominated under 145.A.30(b), (c) and (ca) and the accountable manager. The accountable manager is the person referred to in 145.A.30(a), not one of the (b), (c) or (ca) nominees. The additional categories in 145.A.85(a)(4) and (5), covering the procedure and additional locations, also apply.
All changes to the certificate, including its terms of approval, require prior approval under 145.A.85(a)(1). Apply for and obtain formal approval before implementation; the competent authority amends the certificate and terms of approval as necessary.
Applying for approval and managing other changes
Changes listed in 145.A.85(a), and all other changes requiring prior approval under Part-145, require an application and receipt of formal approval before implementation. All other changes follow the management and notification procedure approved by the competent authority. Under 145.B.330(e), the competent authority includes the review of those changes in its continuing oversight.
For changes requiring prior approval, provide the relevant documentation, await formal approval under 145.B.330, and comply with the operating conditions prescribed by the competent authority during the change. For changes not requiring prior approval, follow the approved management and notification procedure. These routes are not interchangeable.
The MOE procedure must set out the scope of changes not requiring prior approval and how they will be managed and notified; the competent authority approves that procedure under 145.B.310(h). All changes not requiring prior approval remain within its management and notification requirements.
Amend the MOE as necessary so that it remains up to date, and use 145.A.70(a)(10), (a)(11) and (c) for managing and approving amendments, alongside 145.A.85.
Rule text
145.A.85 Changes to the organisation. (a) The following changes to the organisation shall require prior approval by the competent authority: (1) changes to the certificate, including the terms of approval of the organisation; (2) changes of the persons referred to in points 145.A.30(a), (b), (c) and (ca); (3) changes to the reporting lines between the personnel nominated in accordance with points 145.A.30(b), (c) and (ca), and the accountable manager; (4) the procedure as regards changes not requiring prior approval referred to in point (c); (5) additional locations of the organisation other than those that are subject to point 145.A.75(c). (b) For the changes referred to in point (a) and for all other changes requiring prior approval in accordance with this Annex, the organisation shall apply for and obtain an approval issued by the competent authority. The application shall be submitted before such changes take place in order to enable the competent authority to determine that there is continued compliance with this Annex and to amend, if necessary, the organisation certificate and the related terms of approval that are attached to it. The organisation shall provide the competent authority with any relevant documentation. The change shall only be implemented upon the receipt of a formal approval from the competent authority in accordance with point 145.B.330. The organisation shall operate under the conditions prescribed by the competent authority during such changes, as applicable. (c) All changes not requiring prior approval shall be managed and notified to the competent authority as set out in a procedure which is approved by the competent authority in accordance with point 145.B.310(h).
145.B.330 Changes – organisations. (a) Upon receiving an application for a change that requires prior approval, the competent authority shall verify the organisation's compliance with the applicable requirements before issuing the approval. (b) The competent authority shall establish the conditions under which the organisation may operate during the change unless the competent authority determines that the organisation's certificate needs to be suspended. (c) When it is satisfied that the organisation complies with the applicable requirements, the competent authority shall approve the change. (d) Without prejudice to any additional enforcement measures, if the organisation implements changes requiring prior approval without having received the approval of the competent authority pursuant to point (c), the competent authority shall consider the need to suspend, limit or revoke the organisation's certificate. (e) For changes not requiring prior approval, the competent authority shall include the review of such changes in its continuing oversight in accordance with the principles set forth in point 145.B.300. If any non-compliance is found, the competent authority shall notify the organisation, request further changes, and act in accordance with point 145.B.350.
When the current rules apply
The current change-control provisions have applied since 2 December 2022 (Commission Implementing Regulation (EU) 2021/1963).