145.A.75 — Privileges of the organisation

On this page
Regulation section

145.A.75 lists the privileges of a Part-145 organisation, exercised in accordance with the MOE: maintenance, subcontracting, maintenance at other locations, maintenance at line maintenance locations, release to service and Part-ML airworthiness reviews. Each route has its own scope and conditions, and a location used under 145.A.75(c) because of aircraft unserviceability or to support occasional line maintenance is not described as requiring a separate site approval.

How the privileges are exercised

The 145.A.75 privileges are exercised in accordance with the MOE and within the actual terms of the certificate and the MOE scope of work under 145.A.20. The maintenance location routes are in 145.A.75(a), (c) and (d), subcontracting is in 145.A.75(b), and release to service under 145.A.75(e) is subject to 145.A.50; release is not automatic merely because a type is within scope.

Under 145.A.20, the scope of work is specified in the MOE, and the organisation complies with both that scope and the terms attached to its certificate. 145.A.75(a) refers to the locations identified in the certificate and in the MOE, subject to the separate routes in 145.A.75(c) and (d).

The conditions for continued validity in 145.A.90 include remaining in compliance with the regulatory framework specified there, taking into account 145.B.350 on the handling of findings; the competent authority being granted access under 145.A.140; and the certificate not being surrendered, suspended or revoked. The 145.A.75 privileges are exercised within the actual scope of the certificate and the MOE and the applicable conditions.

Point 145.A.80 was deleted by Regulation (EU) 2021/1963 with effect from 2 December 2022. The remaining points 145.A.20, 145.A.75 and 145.A.90, and the applicable task and management requirements, still govern scope, privileges and validity; the deletion did not create an unrestricted permission to carry out maintenance.

Maintenance locations

Under 145.A.75(c), aircraft or components for which the organisation is approved may be maintained at any location when the need arises from the unserviceability of the aircraft or from the necessity of supporting occasional line maintenance, subject to the conditions specified in the exposition. Under 145.A.75(d), a line maintenance location must be capable of supporting minor maintenance, and the exposition must both permit the activity and list the location. These are distinct routes, not an unrestricted permission at every controlled station.

The actual location conditions of 145.A.75(c) and (d) and the permissions and procedures in the MOE apply. A location that is not listed on the certificate is not automatically impermissible if the applicable alternative route is met.

Subcontracting

The subcontracting route in 145.A.75(b), under which the subcontracted organisation works under the organisation's management system, is limited to work permitted by the procedures established under 145.A.65. It excludes a base maintenance check of an aircraft, and a complete workshop maintenance check or overhaul of an engine or engine module. The exclusion covers complete workshop checks as well as overhauls. Contracting an independently approved organisation is not the same as performing work under this subcontracting privilege.

Under 145.A.205, when contracting or subcontracting any part of its maintenance activities, the organisation shall ensure that the maintenance conforms to the applicable requirements and that any aviation safety hazard associated with such contracting or subcontracting is considered as part of the organisation's management system. If the organisation subcontracts any part of its maintenance activities to another organisation, the subcontracted organisation shall work under the scope of approval of the subcontracting organisation.

Release to service

A Part-145 organisation cannot exercise Part-145 release privileges without the corresponding approval and the conditions of 145.A.50 and 145.A.35. This does not mean that every lawful maintenance release in the regulatory framework requires Part-145 approval: the applicable Part-M, Part-ML and Part-CAO routes, and the independent certifying staff and pilot-owner routes, remain separate.

Under 145.A.50, appropriately authorised certifying staff issue the certificate of release to service on behalf of the organisation when the conditions of that point are met. 145.A.35 applies together with the express derogations in 145.A.30(j) for foreign locations, pilots and one-off authorisations.

Part-ML airworthiness reviews

Under 145.A.75(f), the organisation must be specifically approved for aircraft covered by Part-ML and have its principal place of business in a Member State. It may then perform airworthiness reviews and issue the corresponding airworthiness review certificates (ARC) under ML.A.903. ML.A.901(c)(3) additionally places this Part-145 review and issue route within the performance of the 100-hour/annual inspection contained in the aircraft maintenance programme (AMP); 145.A.37 governs the airworthiness review staff.

The Part-ML airworthiness review comprises the documented review and the physical survey described in ML.A.903, with the assistance of appropriate certifying staff where needed. Under ML.A.901, the review may not be subcontracted; the ARC is signed by the airworthiness review staff who carried out the review; an ARC is not issued if there is evidence or there are indications that the aircraft is not airworthy; the review may be carried out 90 days or less before the ARC expires without loss of continuity; a copy of any ARC issued or extended for an aircraft is sent to the competent authority of the Member State of registry of the aircraft concerned within 10 days of the issuance or extension; and on surrender or revocation the ARC is returned to that authority when it so requests. If the review cannot be completed, the competent authority of the Member State of registry must be informed as soon as possible. The details and outcome are recorded in an airworthiness review report.

Text of 145.A.75

In accordance with the MOE, the organisation shall be entitled to carry out the following tasks: (a) Maintain any aircraft or component for which it is approved at the locations identified in the certificate and in the MOE; (b) Arrange for the maintenance of any aircraft or component for which it is approved at another subcontracted organisation that works under the management system of the organisation. This is limited to the work permitted under the procedures established in accordance with point 145.A.65 and it shall not include a base maintenance check of an aircraft, or a complete workshop maintenance check or overhaul of an engine or an engine module;

(c) Maintain any aircraft or any component for which it is approved at any location subject to the need for such maintenance arising either from the unserviceability of the aircraft or from the necessity of supporting occasional line maintenance, subject to the conditions specified in the exposition; (d) Maintain any aircraft and/or component for which it is approved at a location identified as a line maintenance location capable of supporting minor maintenance and only if the organisation exposition both permits such activity and lists such locations; (e) Issue certificates of release to service in respect of completion of maintenance in accordance with point 145.A.50;

(f) If specifically approved to do so for aircraft covered by Annex Vb (Part-ML) and if it has its principal place of business in one of the Member States, the organisation may perform airworthiness reviews and issue the corresponding airworthiness review certificates under the conditions specified in point ML.A.903 of Annex Vb (Part-ML).

Text of 145.A.37 Airworthiness review staff

(a) In order to be approved to carry out airworthiness reviews and to issue the corresponding airworthiness review certificates (ARC) for aircraft covered by Annex Vb (Part-ML), the organisation shall have airworthiness review staff that comply with all of the following requirements: (1) they have acquired experience in continuing airworthiness of at least 1 year for sailplanes and balloons and of at least 3 years for all other aircraft; (2) they hold a certifying staff authorisation for the corresponding aircraft; (3) they have acquired knowledge of Annex I (Part-M), Subpart C, or of Annex Vb (Part-ML), Subpart C; (4) they have acquired knowledge of the procedures of the maintenance organisation relevant to the airworthiness review and issue of the airworthiness review certificate. (b) Before the organisation issues an airworthiness review authorisation to a candidate, that person shall perform an airworthiness review under the supervision of the competent authority or under the supervision of a person that is already authorised as airworthiness review staff by the organisation. If this airworthiness review under supervision is satisfactory, the competent authority shall formally accept that person to become airworthiness review staff. (c) The organisation shall ensure that the airworthiness review staff can demonstrate appropriate recent continuing airworthiness experience.

When the current wording applies

The current wording of the introductory text and points (a), (b) and (f) of 145.A.75, and of 145.A.37, has applied since 2 December 2022 (Regulation (EU) 2021/1963). Points (c), (d) and (e) of 145.A.75 retain their earlier wording from Regulation (EU) No 1321/2014. Quoting an EU derogation does not by itself establish qualification or recognition under a foreign jurisdiction.

Part 145 Training

Ready to master Part 145 compliance?

Go beyond the regulation text. Sofema's Part 145 course covers practical compliance strategies, quality system obligations, and real audit scenarios.

View Part 145 course

Sources

Next step Sofema Aviation Academy

Courses for 145.A.75

EASA Part 145 Regulation EU 1321/2014 (Part 145 Initial) with VO

2.5 days · Voice Over

Why: covers Part-145 requirements as a whole.

View course

Related training, not a regulatory requirement. Check course scope and prerequisites before enrolling.

A different role or training goal? Course Finder

Educational reference, not legal advice. Verify against the current Official Journal text linked under Sources. How this hub is made.