Optimizing the Performance of Part 145 Organisations

Production Planning Makes the Difference & Driving Continuous Improvement

29-06-2026
9 Min read

In an EASA or FAA Part 145 aircraft maintenance environment, Production Planning is frequently misconstrued as a purely administrative support function, responsible only for scheduling tasks and logging man-hours.




Whereas In reality, effective production planning functions as the core operational interface. It directly bridges the gap between commercial availability demands and hangar-floor technical execution, wielding immense influence over safety, structural efficiency, and bottom-line profitability.



Key Areas Strongly Influenced by Production Planning Staff


Production planning personnel sit at a critical crossroads intersecting logistics, engineering, operations, and finance. Their strategic decisions and foresight directly ripple across primary areas:


  • · Turnaround Time (TAT) and Hangar Dwell Time: Planning staff directly control the velocity of an aircraft check.
  • · Through meticulous task sequencing, they systematically eliminate "dead time" and ensuring that critical path milestones are precisely met.
  • · Resource and Capacity Utilization: Labor represents one of a Part 145 organization’s highest ongoing operating costs. Planners directly determine whether technicians are working efficiently or sitting idle due to missing components or poorly sequenced task cards.
  • · Material Availability and Supply Chain Synchronization: A substantial percentage of maintenance delays are driven by being "Awaiting Parts" (AWP). Planners mitigate this exposure by   aggressively pre-loading material requirements, validating specialized tool availability, and coordinating with procurement workflows long before the aircraft arrives at the hangar line.
  • · Facility and Ground Support Equipment (GSE) Optimization: Hangar bays, docking systems and specialized avionics test sets are finite resources.
  • · Risk Mitigation and Defect Inflow Management: Opening up an airframe invariably uncovers unexpected defects (non-routines). Competent planners analyze historical reliability data for specific aircraft types, variations, and ages to embed realistic "buffers" into the schedule, absorbing the technical shock of defect rectifications without breaching the delivery commitment



Key Performance Indicators (KPIs) for Production Planning

​

To accurately determine whether a production planning department is driving efficiency, organizations must


  • · Implement robust metrics. These indicators focus specifically on planning accuracy, structural logic, and predictive capability, isolated from direct hangar execution variables.
  • · Hangar Efficiency & Timeline Metrics
  • · Turnaround Time (TAT) Adherence Rate: Expressed as the percentage of maintenance inputs successfully completed and released on time relative to the total number of checks scheduled. This evaluates overarching planning accuracy and critical path management.
  • · Milestone Achievement Index: This tracks the percentage of internal gate milestones achieved on time, including defueling, structural stripping, inspection freeze, and final close-up. Measuring these gates isolates exactly where a check begins to deviate before the delivery schedule is compromised.
  • · Schedule Effectiveness: Calculated as the ratio of planned hours earned compared against actual hours expended, expressed as: Schedule Effectiveness = (Planned Hours Earned ÷ Actual Hours   Expended). (This validates how realistic and operationally sound the original production baseline schedule was.)
  • · Resource & Labor Metrics - Direct vs. Indirect Labor Ratio: The tracking of hours billed directly to a maintenance work package - versus unassigned, unbilled, or waiting time.



o High indirect ratios indicate systemic sequencing failures, logistics blockages, or planning delays on the hangar floor.


  • · Man-Hour Burning Rate: A metric monitoring the daily velocity of consumed man-hours mapped against the planned linear or sigmoidal curve.


o This provides early warning indicators of potential labor cost overruns or critical under-resourcing on specific shifts.


  • · Pre-Load Material Service Level: The percentage of planned components and consumable kits physically staged and available at the start of the check compared to total planned material requirements:


o Service Level = (Staged Parts ÷ Total Required Parts) × 100. Organizations should drive planning staff toward a baseline target exceeding 95%.


  • · Awaiting Parts (AWP) Downtime: The cumulative number of hours an aircraft check is completely stalled awaiting components, tooling, or essential engineering data. This serves as a primary indicator of pre- planning gaps or flawed material coordination.
  • · Non-Routine vs. Routine Ratio: The numerical relationship between predicted routine tasks and unpredictable defects discovered during inspection phases. Planners utilize this historical ratio to dynamically size realistic schedule buffers tailored to specific tail numbers and operating environments.
  • · Post-Release Deferred Items: The total volume of non-safety-critical, deferred defects permitted at the final aircraft release.



o A high number of deferred items implies that the production schedule forced corners to be cut to hit a commercial deadline, shifting the maintenance burden onto line operations.




The Post-Check Production Planning Meeting: Closing the Loop

​

The Post-Check Production Planning Meeting (commonly referred to as the Wash-Up or Debrief Meeting) represents the definitive phase of the production planning cycle. Without this final step, planning operates as an open loop, meaning systemic errors are continuously repeated, and master schedules remain unoptimized.


This meeting converts raw hangar-floor operational performance data into refined, structured intelligence to drive continuous improvement for subsequent inputs.


  • · Maximizing Impact and Embedding Structural Improvements
  • · Work Package Baseline Calibration: Planners cross-reference estimated man-hours per task card against actual clocked labor times. If a routine task consistently demands four actual hours instead of the engineered two-hour baseline, planners update the master planning data to prevent permanent, systemic under-scheduling.
  • · Refining Non-Routine Predictability: Defect rectifications are inherently variable, but clear statistical patterns exist.
  • · Post-check reviews allow planners to map out high-probability defects based on fleet maturity or operator usage, allowing them to pre-stage complex materials and adjust labor capacity in advance.
  • · Optimizing Material and Tooling Kits: When a technician loses productive hours locating a specialized tool or waiting on basic consumables, the post-check meeting exposes the log breakdown. Planners use this to re-engineer standard "pre-load" bills of material, ensuring those exact tools and parts are automatically bundled together.
  • · Inter-Departmental Handover and Gate Synchronization: The wash-up meeting clarifies friction points between opposing shifts, or between planning, logistics, and Compliance - Quality Assurance (QA). Planners use these insights to alter shift overlap durations or re-sequence internal milestone gates to protect the critical path.




KPIs for Measuring Post-Check Learning and Continuous Improvement

​

  • Task Estimate Variance Rate: The percentage difference between the pre-planned man-hour target on a task card and the actual clocked execution hours. A narrowing variance across consecutive inputs validates that post-check feedback is effectively tuning the planning baseline.
  • · Recurring Delay Frequency: The absolute tracking of how frequently an identical bottleneck (e.g., waiting for external composite shop sign-offs or specific NDT equipment availability) occurs across sequential checks. Post-check interventions should force this metric toward zero.
  • · Feedback Implementation Rate: The percentage of formal "lessons learned" action items registered during the wash-up that are actively engineered into the ERP or master planning software prior to the very next identical check input.
  • · Kitting Accuracy Index: The mathematical ratio of components and tooling successfully utilized from pre- arranged maintenance kits versus items that had to be ad-hoc ordered mid-check. Consistent post-check calibration should drive this index up.
  • · Buffer Utilization Efficiency: Measures the exact proportion of scheduled defect buffer time that was consumed. If buffers are never touched, the schedule is unnecessarily loose; if they are always exceeded, the schedule is too aggressive. Post-check data continuously refines this operational sweet spot.



Core Discussion Takeaways for the Management Team:

​

Data Integrity: Production planning is strictly bound by the quality of input data received from Engineering and Continuing Airworthiness Management Organizations (CAMO). If the input work packages are poorly defined, floor optimization is structurally impossible.

Proactive Mindset: The organizational culture must shift the planning department away from historical tracking ("what happened yesterday") and focus them heavily on predictive scheduling ("smoothing bottlenecks 3 to 5 days out").

The Financial Return: Allocating resources to professional planning training and robust scheduling toolsets pays immediate dividends by mitigating ground penalties, shortening TAT, and extracting maximum utility from high-cost technician labor.



Next Steps 

Sofema Aviation Services (SAS) and Sofema Aviation (SA) Provide Classroom, Webinar & Online training. Explore 525+ aviation courses at Sofema, or contact [email protected] for support.

​

Tags:Part 145MROSofema Aviation (SA)Aircraft MaintenanceProduction PlanningContinuous ImprovementHangar OperationsAviation LogisticsTurn around Time

Found this useful?

Share it with your network on LinkedIn.

Share on LinkedIn
Back to Blog